Carnac and Vikhroli flyovers inching towards completion, says BMC
According to BMC, the solid approaches on both ends of the Carnac Bridge have been completed. The deck slab on the western side is ready, and 40 of the 80 metres on the eastern side have also been completed and are currently undergoing curing